Lift Station #13 and Force Main Replacement Project

Page Title

Page Title

Lift Station 13 Project Map

35.524305, -120.703112

email: publicworks@atascadero.org

main phone: 805-470-3456

Quick Overview

This project will include replacing Lift Station No. 13 and Force Main; and pavement rehabilitation for Traffic Way between Carrizo Road and Chico Road. 

 

LS #13 Map

 

 

 

CONSTRUCTION UPDATES 

 

Weeks of 12/23/24 - 1/03/25:
• Lift-station work continues on-site at El Camino Real (at Santa Cruz Road). 

 

 

Construction schedules are subject to change based on staffing, supplies, and weather conditions.

 

 

 

 

 

 

 

 

Project Overview

This project involves replacing Wastewater Lift Station #13 and constructing approximately 2 miles of force main pipe between El Camino Real and Orillas Way below Santa Cruz Road and Traffic Way.

This project includes the Traffic Way Pavement Rehabilitation - North Project, which includes pavement rehabilitation for approximately 1.1 miles of Traffic Way between Carrizo Road and Chico Road.

Project Timeline 

Design Development:  

  • June 2021 – September 2021 

Engineering Design:  

  • October 2021 – September 2023 

Construction:  

  • Spring 2024 – Spring 2025 

Project Cost and Funding Sources:

  • Budget $8,735,000  
  • Funded by:
    • Wastewater Funds: FY2023-25 Budget ($7,435,000)
    • Road Repair and Accountability Act Funds: FY2023-25 Budget ($800,000)
    • Road Repair and Accountability Act Funds: Additional Funding ($500,000)

Project Resources:

10/12/21 City Council Agenda Packet: Staff Report for Lift Station No. 13 and Force Main Replacement Project Engineering Design Award

8/9/22 Council Agenda Packet:  Motor Control Center (TESCO) expenditures approved at Council

11/14/23 City Council Agenda Packet: Staff Report for Lift Station No. 13 and Force Main Replacement Project Construction Award

11/28/23 City Council Agenda Packet: Minutes for Awarding Construction Management and Construction Contracts