This project involves replacing Wastewater Lift Station #13 and constructing approximately 2 miles of force main pipe between El Camino Real and Orillas Way below Santa Cruz Road and Traffic Way.
This project includes the Traffic Way Pavement Rehabilitation - North Project, which includes pavement rehabilitation for approximately 1.1 miles of Traffic Way between Carrizo Road and Chico Road.
Project Timeline
Design Development:
- June 2021 – September 2021
Engineering Design:
- October 2021 – September 2023
Construction:
- Spring 2024 – Spring 2025
Project Cost and Funding Sources:
- Budget $8,735,000
- Funded by:
- Wastewater Funds: FY2023-25 Budget ($7,435,000)
- Road Repair and Accountability Act Funds: FY2023-25 Budget ($800,000)
- Road Repair and Accountability Act Funds: Additional Funding ($500,000)
Project Resources:
• 8/9/22 Council Agenda Packet: Motor Control Center (TESCO) expenditures approved at Council