Skip to main content

Downtown District Pavement Rehabilitation Project

Downtown Paving project work

35.490094, -120.668733

email: publicworks@atascadero.org

main phone: 805-470-3456

Quick Overview

This project included upgraded curb ramps, improved street surfacing, and striping throughout the Downtown area. 

CONSTRUCTION UPDATE

Downtown Paving Project Update

 

Projected Work after 4/26/24:

• No additional work is expected other than final punch-list items.

• Thank you for your patience during the Downtown District Pavement Rehabilitation Project!

 

 

 

 

 

 

 

 

Project Overview

As part of the City Council’s Key Priorities, the City of Atascadero approved the Downtown District Pavement Rehabilitation Project.  The project included upgraded curb ramps, improved street surfacing, and striping.

This paving project took place in two phases throughout the Downtown area. The first phase began in September, 2023 and included removal and replacement of various curbs, gutters and ramps.

Phase two began in early November, 2024 and included paving work on streets. Streets included in the Downtown paving project are Entrada, Palma Ave., East and West Mall, Lewis Ave., the city alleyways behind the West Mall and Entrada Avenue businesses and behind the Carlton Hotel, and the parking lot near the northwest corner of Palma and Traffic Way.

The City appreciates everyone’s patience as we completed this important project!  

Project Timeline 

Engineering Design:  

  • August 2022 – June 2023 

Construction:  

  • Phase 1 began September 18, 2023
  • Phase 2: November 2023 - April 2024

Project Cost and Funding Sources:

  • Budget $2,002,340  
  • Funded by Local Transportation Funds