Bernards presented an update at the City Council meeting on the evening of July 27. The Power Point presentation slides are attached to this web page for public review. Bernards estimating has been working closely with the subcontract market to better identify the expected budget for the entire project. It was reported that the expected overall budget was trending towards an reduction in cost. The City Council approved Bernards’ recommendation of a Construction Management Multi-Prime (CM/MP) contract delivery method. The CM/MP delivery will allow for an earlier start of actual work as well as help to eliminate a number of redundancies in contractor overhead and profits.

Bernards Presentation to the City Council