The Historic City Hall basement Electrical Demolition and Temporary Power installation is complete.  The basement hazardous materials abatement, concrete wall and floor demolition contractor mobilized on Wednesday December 15th and began containment setup of basement rooms requiring abatement.  Temporary site lighting is complete.  All abatement setup was confirmed acceptable by the Hazardous Materials monitoring firm, Millennium, Inc.  Basement abatement began on Friday December 17th.

 