The penthouse demolition contractor mobilized this week.  The fourth level rotunda floor was cleared of pigeon excrement for the contractors path of travel to perform abatement and demolition of the existing penthouse structures.  Preparation for abatement began with the removal of all the loose brick on the roof.  The brick was palletized and wrapped for storage for future reinstallation.  Prior to reinstall, the loose brick will be cleaned and prepped for reuse.  In addition, all existing surplus equipment was removed; existing kitchen fixtures, light sconces from the penthouse apartment, and historic radiators to name a few.  Roof and lead abatement will begin during the school’s Spring Break (April 18th thru April 22), including the removal of the penthouse structures.

 