Penthouse demolition continues.  The Club House, East Apartment, and 80% of the Kitchen penthouse structures have been removed.  All debris was removed from the roof and loaded into the onsite bins for disposal.  Next week the balance of the kitchen perimeter walls will be removed for disposal.  The West Apartment removal will follow.  Once all structures are removed the penthouse concrete topping slabs will be removed to complete demolition.  Once complete, building protection will be put in place to protect all exposed openings following the penthouse demolition.  The future contractors will maintain the building protection throughout the duration of work on the Historic City Hall.

 

 